Memorials up to 10 metres tall could go up at the National Memorial Arboretum without separate planning applications. Comments are open until 18 December.

New memorials at the National Memorial Arboretum near Alrewas could go up without a planning application for each one. A draft Local Development Order for the site was lodged with Lichfield District Council on 16 November.

The site has been called the Royal British Legion National Remembrance Gardens since the arboretum’s charity merged with the Legion on 1 April 2026. The draft order says the gardens grew “organically”, with no single planning permission covering the site. That means a “constant need” to apply for what are “often uncontentious small scale” memorial schemes.

The draft order and its statement of reasons are on the council’s planning file under reference 26/01363/LDO.

Overview

  • What: a Local Development Order granting standing planning permission for memorials and related buildings at the National Memorial Arboretum, Croxall Road, Alrewas.
  • Biggest memorial allowed: up to 10 metres tall, with paving or planting up to 10 metres by 10 metres.
  • Where nothing can be built: a prehistoric scheduled monument by the River Tame and a Second World War pillbox.
  • Comments: the council’s consultation runs until 18 December 2026.
  • Decision due: by 12 January 2027, according to the planning file.

What the order would allow

An order of this kind grants planning permission in advance for set types of work, within limits written into it. The draft splits the gardens into three areas, drawn around flood risk, heritage and wildlife.

In Area 1, the drier ground around the Remembrance Centre and the car parks, the order would permit:

  • memorials up to 10 metres tall, with seating, stones and paving
  • new and extended storage buildings for plant and equipment
  • toilet blocks, classrooms and meeting rooms
  • new paths and resurfaced paths
  • canopies no more than 4 metres high

Area 2 lies in flood zones 2 and 3, the medium and high risk zones. It includes the Armed Forces Memorial and the UK Police Memorial. Here the order would permit:

  • memorials up to 10 metres tall, with no more than 250 square metres of hard surface in total
  • an extension of up to 250 square metres to one existing building, for classrooms, meeting rooms and toilets
  • an extension of up to 100 square metres to another, for toilets and extra space
  • one shelter of up to 100 square metres that lets flood water flow through
  • new paths at existing ground level

No ground levels may be changed in Area 2. The Environment Agency’s advice on the file notes that any significant earthworks for a memorial would still need separate planning approval.

Area 3 is the site of a round barrow near the River Tame, a scheduled monument, with a buffer around it. It also covers a Second World War pillbox to the north. No development at all would be allowed there.

The order also covers smaller works across Areas 1 and 2. These include flagpoles, CCTV poles up to 4 metres, temporary CCTV masts up to 10 metres for events, fences up to 4 metres, low bollard lighting, signs, benches, EV charging posts and cycle parking.

It would not replace building regulations, advertisement consent or scheduled monument consent. The council would review it after five years.

The monument the order would protect

The statement of reasons describes the scheduled monument as a prehistoric ring ditch, about 310 metres north east of the visitor centre. A geophysical survey in 2023 found it “survives well” where it was not cut away. The survey also found that the area on the official schedule is in the wrong place.

The surveyors now think it may be a Neolithic henge, later reused for a round barrow. Area 3 has been drawn around the newly surveyed position, the statement says, in consultation with Historic England.

What the advisers said before it was lodged

The file holds advice given in August, before the draft was submitted, alongside the first response to the council’s own consultation:

  • Environment Agency (10 August): “Such an approach is welcomed.” It raised no significant concerns about the scale of work in the flood zones. It said it understood that up to about seven large memorials a year were expected, and asked whether an annual limit could be written into the order.
  • Historic England (18 August): it supports a no-works area over the barrow. It says the official map of the scheduled monument is wrong and has not yet been corrected. It would also support existing memorials and planting that sit on the barrow’s eastern side being “progressively moved and relocated” outside its footprint.
  • Staffordshire County Council rights of way team (20 November): it could not comment yet. It said public rights of way cross the site but are not shown on any of the plans, and asked for that information.

Visitor numbers

The gardens opened to the public in May 2001. Figures submitted with the order show how visits grew after the Armed Forces Memorial was dedicated in 2007.

Bar chart of annual visitors to the National Memorial Arboretum: 18,749 in 2002, 130,034 in 2007, 294,792 in 2008, 322,807 in 2018, 310,960 in 2019, 148,115 in 2020 and 299,344 in 2022
Annual visitors in selected years. Source: visitor numbers submitted with application 26/01363/LDO. Chart by Lichfield Today
Share this chartFacebookWhatsAppX
Year Visitors
2002 18,749
2007 130,034
2008 294,792
2018 322,807
2019 310,960
2020 148,115
2022 299,344

The 2020 total includes no visitors at all in April and May. The draft order puts today’s figure at “over 300,000” a year. It says any extra visits from work under the order would stay within the forecasts in the 2012 transport assessment for the Remembrance Centre. That assessment planned for up to 500,000 visitors a year and 2,500 on the busiest days.

What it means for you

If you live in Alrewas or along Croxall Road, the order would mean fewer individual planning applications to watch at the arboretum. Memorials, toilets and classrooms within the limits above would no longer come to the council one by one.

You can comment on the draft order through the council’s planning portal, quoting 26/01363/LDO. The consultation closes on 18 December. A press notice for the order runs until 2 January 2027.