Gladman plans up to 800 homes on fields off Comberford Road, on Tamworth's edge in Lichfield district. National Highways says the traffic case is not yet made.

Gladman Developments plans to apply for up to 800 homes on 46 hectares of farmland off Comberford Road, on the northern edge of Tamworth. The fields sit inside Lichfield district, in Wigginton and Hopwas parish, about six miles east of Lichfield city centre.

The scheme would also set aside land for a possible primary school and a small shop. The plans are set out in an environmental scoping report Gladman sent to Lichfield District Council in September.

The council issued its scoping opinion on 13 November, the planning register shows. That decides what Gladman’s environmental statement must cover. It is not planning permission, and no application has been made yet.

Overview

  • What: up to 800 homes, land for a potential primary school, land for a potential small shop and public open space.
  • Where: about 46 hectares of fields between the A513 Comberford Road, Wigginton Lane and Comberford Lane, north of Tamworth and west of Wigginton village.
  • Who: Gladman Developments Ltd. The register names Tor & Co, of Bournemouth, as the applicant for the scoping opinion.
  • Reference: 26/01170/SCOPE. Scoping opinion issued 13 November 2026.
  • Next: Gladman says it intends to apply for outline planning permission.

What Gladman is proposing

The scoping report says the site is “several large arable fields” with hedgerows, a small watercourse and a public footpath, Wigginton and Hopwas 9, running across it.

It sets out these features:

  • two new road junctions onto the A513 Comberford Road
  • a 30mph limit “envisaged” on the stretch of Comberford Road beside the site
  • the footpath kept, with new walking and cycling links
  • a wide strip of open space in the north east, as a buffer to Wigginton Conservation Area
  • solar panels and air-source heat pumps, and no gas supply to the site

Lift Rawlett School and The Coton Centre border the fields to the south west.

Schools and GPs nearby

The report sets out how busy local services already are. It says St Leonard’s CE (VA) Primary School in Wigginton, whose catchment covers the site, is over capacity. Ashcroft Infant and Nursery School in Tamworth has spare places, and Flax Hill Junior Academy is approaching capacity. Lift Rawlett School, the catchment secondary, has spare capacity.

Every GP practice in the site’s catchment has more patients per full-time GP than the 1,800 benchmark the report uses:

GP practice Patients per full-time GP
Laurel House Surgery 2,973
Riverside Surgery 2,416
The Aldergate Medical Practice 2,356
The Peel Medical Practice 1,977
Hollies Practice 1,858

National Highways: the traffic case is not yet made

Gladman’s report proposed leaving traffic out of the environmental assessment and covering it in a separate transport assessment instead.

National Highways disagreed. In its response of 13 November, it said there was “insufficient evidence to justify scoping traffic and transport effects out of the EIA at this stage.”

It said the report gave no trip figures or junction capacity evidence. It also noted that the report itself accepts traffic on Comberford Road is likely to rise by more than 10%. The report names existing congestion at the A453 and A5 junction and at the A5 and M42 junction.

National Highways said it had given advice before on a scheme for up to 700 homes on the same site. The rise to 800, it said, “further emphasises the need for robust evidence”.

Why the council’s housing numbers matter

Gladman’s report leans on the council’s own figures. It cites the January 2026 statement showing a 3.5-year supply of deliverable housing land, against the five years councils are expected to show. It also says 597 homes were completed in the district in 2024/25, below the need figure of 746 a year.

When a council cannot show a five-year supply, national policy makes it harder to refuse housing on land not allocated in its plan. The council is now preparing a new Local Plan to 2046, with its call for sites open until 30 November.

What it means for you

There is nothing to comment on yet. When Gladman applies, the application will appear on the council’s planning register with its own reference and a deadline for comments.

The council’s scoping opinion itself was not on the register when we checked on 17 November. The consultee responses are, including those from the Environment Agency, Natural England and the county’s flood team.